Twitter

Pages

Monday, April 5, 2010

Construction update April 5/10

Roofers are progressing well and should have 50 per cent of building watertight tonite.

Everstrong to place additional fans around the building helping to dry out walls.

Topping on 2nd floor to be poured next week and Painter to start within 2 weeks.

Exterior brick veneer is progressing well and Mason contractor should be commplete by May 1.

Sidewalk and curbs are schelduled for the 1st week of May.

Larry

No comments:

Post a Comment